Indiana Finance Authority Issues the Request for Qualifications for the I-69 Section 5 Project

On the heels of its very successful foray into availability payment model public-private partnership (“P3”) concessions, the Indiana Finance Authority (“IFA”) issued its second P3 Request for Qualifications (“RFQ”) on May 23, 2013, this one to develop, design, build, finance, operate and maintain the I-69, Section 5 project.  As with the preceding P3 procurement of the East End Crossing (part of the broader Ohio River Bridges Project), the I-69 Section 5 project will be a public-private partnership between the State of Indiana, through the IFA and the Indiana Department of Transportation (“INDOT”) and the successful proposer. 

The I-69 Section 5 project consists in upgrading approximately 21 miles of existing State Route (“SR”) 37, a four-lane median divided highway between Bloomington, Indiana (home of Indiana University) and Martinsville, Indiana, and development of a six-lane divided highway in designated urban areas.  In addition, the project involves construction of four new interchanges and four new overpasses with varying degrees of improvements to the existing interchanges and overpasses at the Fullerton Pike, Tapp Road/SR 45/2nd Street, Sample Road and Liberty Church Road, all of which are current intersections with SR 37.

Section 5 is one of six sections under development to complete the interstate connection from Evansville, Indiana to Indianapolis, collectively part of a further development of the national I-69 corridor to connect Mexico with Canada.  Four of the remaining five sections are completed or development and construction are underway, and Section 6 is still in the planning stage.

Over 175 people attended a industry workshop on May 22, where Governor Mike Pence reaffirmed Indiana’s, and his administration’s, commitment to exploring innovative approaches to deliver much-needed infrastructure – particularly transportation – improvements in Indiana.

IFA is an independent financing instrumentality of the State, which in working with INDOT, reprises a successful partnership that brought the East End Crossing to the American P3 industry, the first availability payment concession in the United States to have met each of its procurement schedule deadlines in among the fastest P3 procurements in the United States and to have successfully achieved financial close with a “flat” investment grade rating.

Statements of qualifications are due at the IFA’s offices in Indianapolis, Indiana at 3:00 p.m. on July 9, 2013.  Shortlisting is anticipated by the end of July 2013, with award tentatively scheduled for late first quarter, 2014 and financial close early second quarter, 2014.

Trackbacks (0) Links to blogs that reference this article Trackback URL
http://www.infrainsightblog.com/admin/trackback/300357
Comments (0) Read through and enter the discussion with the form at the end
Nossaman LLP
Los Angeles 777 South Figueroa Street
34th Floor
Los Angeles, CA 90017
T 213.612.7800
F 213.612.7801
Washington, DC 1666 K Street, NW
Suite 500
Washington, DC 20006
T 202.887.1400
F 202.466.3215
San Francisco 50 California Street
34th Floor
San Francisco, CA 94111
T 415.398.3600
F 415.398.2438
Arlington 2111 Wilson Boulevard
Suite 700
Arlington, VA 22201
T 703.682.1750
Orange County 18101 Von Karman Avenue
Suite 1800
Irvine, CA 92612
T 949.833.7800
F 949.833.7878
Austin 919 Congress Avenue
Suite 1050
Austin, TX 78701
T 512.651.0660
F 512.651.0670
Sacramento 621 Capitol Mall
25th Floor
Sacramento, CA 95814
T 916.442.8888
F 916.442.0382