California Supreme Court Allows Presidio Parkway to Proceed as P3

On November 16, challenges to the legality of the Presidio Parkway public-private partnership (P3) contract ended with a one sentence order from the California Supreme Court: “The petition for review is denied.”  Professional Engineers in California Government (PECG), the union representing Caltrans engineers, had asked the Supreme Court to review the Aug. 8, 2011, decision of the California Court of Appeal in San Francisco (First District), which unanimously held that Phase 2 of the Presidio Parkway project can move forward as a P3.  As a result, the California Department of Transportation (Caltrans) and the San Francisco County Transportation Authority (SFCTA) will continue with Phase 2.  The project will replace the old and outmoded approach to the Golden Gate Bridge in San Francisco.  The Supreme Court’s action denying the petition comes a year after PECG filed the lawsuit in the trial court.

When the California Transportation Commission considered whether to approve use of a P3 for the project under Streets and Highways Code section 143, the California Legislative Analyst Office (LAO), and the California Attorney General’s office (AG) as counsel to the Commission, gave written opinions concluding that the project was not authorized.  Caltrans’ general counsel, along with Nossaman acting as P3 legal advisor to Caltrans, took a contrary position.  Section 143, adopted in 2009, broadens the types of P3 projects authorized in California.  The Commission approved the project for a P3, while noting the unresolved legal issue.

PECG sued Caltrans and the SFCTA to stop Phase 2 of the project, arguing, like the LAO and AG had earlier, that the project was not authorized by section 143.  The courts rejected PECG’s argument that, under section 143, Caltrans’ internal personnel must perform all the preliminary planning and design services, as opposed to being responsible only for seeing them done correctly.  The courts also rejected the argument that P3 efforts under California law must be confined to toll projects, holding that the legislation authorized much broader use of innovative financing, in this case an availability payment.  Finally, the courts also held that the project was properly characterized as supplemental to existing facilities, as required by section 143.

The Presidio Parkway Project is the first project to reach award under California’s new P3 statute.  The decision of the courts—and now the finality—is important beyond the Presidio Parkway Project.  This should ease the way to use P3s under section 143 for other projects, and also provide helpful precedent for design build projects authorized under parallel legislation passed at the same time.

At the beginning of 2011, Caltrans, in cooperation with SFCTA, signed a contract for the project to Golden Link Concessionaire, LLC, a consortium led by Hochtief  PPP Solutions North America and Meridiam Infrastructure North America. 

Nossaman represented SFCTA in the litigation and advised Caltrans during the P3 procurement.  Caltrans was represented in the litigation by its own department counsel.

For more about the Presidio Parkway Project and section 143, see Appeals Court Rules Presidio Parkway Can Move Forward as P3, Presidio Parkway Project Awarded, Preferred Proposer Selected for Presidio Parkway Project, Final RFP for the Presidio Parkway Project Released, Presidio Parkway Reaches Two Important Milestones, and Presidio Parkway Project RFQ Issued.

Update: Proposed Legislation Threatens Design-Build and P3s in California

Fred Kessler co-authored this post.

We are pleased to report that AB 294--the bill that was the subject of our blog yesterday--is no longer in play. 

Proposed Legislation Threatens Design-Build and P3s in California

Fred Kessler co-authored this post.

A last-minute amendment to California Assembly Bill 294, if passed, would wreak havoc on Caltrans and local agency plans to use design-build for state highway projects (Public Contract Code section 6800 et seq.) and to enter into public-private partnerships (P3s) for highway projects (Streets and Highways Code section 143).
 
The language added to the bill would preclude local agencies from hiring consultants to work on the projects, stating that all work must be done through Caltrans employees or consultants under contract with Caltrans.  Project consultants are often hired well in advance of the decision to use design-build or P3s for the project--which means that this bill would create significant inefficiency by requiring new consultants to be brought on board once that decision is made.   

Given the existing sunsets for P3 projects (January 1, 2017) and design-build projects (January 1, 2014), this bill could make public-private partnerships and design-build a hollow tool for California highway projects.
 
This appears to be an attempt by the Professional Engineers in California Government (PECG) to do an end-run around a recent California appellate court ruling regarding the Presidio Parkway P3 agreement.  Although the legislation would not affect contracts that have already been awarded, such as the Presidio Parkway agreement, the bill would impact future P3 projects under Section 143 and future design-build projects under Section 6800, possibly including some projects that are already in the procurement process.  In the Presidio Parkway case, PECG sought a determination that the agreement was invalid because engineering consultants under contract with the San Francisco County Transportation Authority performed services on the project while section 143 allegedly requires the consultants to be under Caltrans direct contract and supervision.  Caltrans and the SFCTA have pursued the project for many years under a series of cooperative agreements.
 
The bill, authored by Assemblyman Portantino, was originally short-titled "Design-sequencing contracts" and is now called "Transportation projects: procurement."  It would appear more appropriate to call it "Increased inefficiency in government."
 
The legislative session closes at the end of next week (September 9), and September 2 is the last day to amend existing bills.  It seems likely this bill will make it to the floor.  The authors of this blog urge readers to contact their legislators and ask them to oppose the bill.

Appeals Court Rules Presidio Parkway Can Move Forward as P3

On August 8, 2011, the 1st District Court of Appeal in San Francisco published a decision holding that Phase 2 of the Presidio Parkway project can move forward as a public-private partnership (P3).  The unanimous opinion approved of and affirmed the February decision by Judge Wynne Carvill of the Alameda County Superior Court to the same effect, allowing the California Department of Transportation (Caltrans) and the San Francisco County Transportation Authority (SFCTA) to proceed with Phase II as a P3. The decision was issued less than five months after the appeal had been taken, because Caltrans and SFCTA had asked the Court to expedite what would normally be a longer process in order to get the critical project moving forward promptly.

Professional Engineers in California Government (PECG), the union representing Caltrans engineers, sought to stop Phase II of the project, which is replacing the old and outmoded approach to the Golden Gate   Bridge in San Francisco.  PECG sued Caltrans and the SFCTA, arguing that the project was not authorized by Streets and Highways Code section 143, recent legislation broadening the types of P3 projects that could be performed in California.  However, the Court of Appeal rejected PECG’s argument that, under section 143, Caltrans employees or direct consultants must perform all the preliminary planning and design services, as opposed to being only responsible to see them done correctly.  The Court also rejected PECG's other arguments, that the project was not supplemental and that P3 efforts under California law must be confined to toll projects, holding that the legislation authorized much broader use of innovative financing, in this case an availability payment.

The Presidio Parkway Project is the first project to reach award under California’s new public-private partnership statute.  This decision should ease the way for other projects, and also provide helpful precedent for design build projects authorized under parallel legislation.

At the end of 2010, Caltrans, in cooperation with SFCTA, signed a contract awarding the project to Golden Link Concessionaire, LLC, a consortium led by Hochtief PPP Solutions North America and Meridiam Infrastructure North America.

PECG will have until September 16 to ask the California Supreme Court to review the Court of Appeal decision.  It is not known if PECG will seek review, however the Supreme Court grants review in only a small number of cases based on specific criteria.

Nossaman represented SFCTA in the litigation and Caltrans was represented by its own Department counsel. Nossaman has also provided assistance to Caltrans in the procurement of the project.

For more about the Presidio Parkway Project and section 143, see Presidio Parkway Project Moves Forward as Court Denies Request for Writ of Mandate and Injunction, Presidio Parkway Project AwardedPreferred Proposer Selected for Presidio Parkway Project, Final RFP for the Presidio Parkway Project Released, Presidio Parkway Reaches Two Important Milestones, and Presidio Parkway Project RFQ Issued.

Presidio Parkway Contract Awarded

The California Department of Transportation started off the New Year with a significant step in its public-private partnership program.  After an Alameda County Superior Court judge dissolved a temporary restraining order and denied a preliminary injunction sought by Professional Engineers in California Government, the California Department of Transportation, in cooperation with the San Francisco County Transportation Authority, awarded the contract for the Presidio Parkway Project to Golden Link Concessionaire, LLC, a consortium led by Hochtief PPP Solutions North America and Meridiam Infrastructure North America.  Golden Link Concessionaire, LLC proposed a maximum availability payment of $28,549,189 for the 30-year contract to design, build, finance, operate, and maintain the Presidio Parkway Project.
 
The Presidio Parkway Project in San Francisco is the first project to reach award under California's new public-private partnership statute, Streets and Highways Code section 143. For more about the Presidio Parkway Project and Section 143, see Preferred Proposer Selected for Presidio Parkway Project, Final RFP for the Presidio Parkway Project Released, Presidio Parkway Reaches Two Important Milestones, and Presidio Parkway Project RFQ Issued.

Final RFP for the Presidio Parkway Project Released

Following extensive industry review of the draft Request for Proposals, on Friday, July 9, 2010, the California Department of Transportation, in coordination with the San Francisco County Transportation Authority, issued the final Request for Proposals for the Presidio Parkway Project. According to the latest procurement schedule in the Request for Proposals, technical proposals are due on September 10, 2010, and financial proposals are due on September 24, 2010.

The Presidio Parkway Project is the first public-private partnership procurement under California's new public-private partnership law, Section 143 of the Streets and Highways Code. For more about the Presidio Parkway Project and Section 143, see Presidio Parkway Reaches Two Important Milestones and Presidio Parkway Project RFQ Issued.

Presidio Parkway Reaches Two Important Milestones

California's first public-private partnership procurement has passed two major hurdles in the last week.  First, after a long anticipated and much-debated hearing, the California Transportation Commission approved the San Francisco Presidio Parkway Project last week on an 8-3 vote.

Second, on May 25, the California Department of Transportation released the draft request for proposals to design, build, finance, operate and maintain the Presidio Parkway.  The project, sponsored by Caltrans and the San Francisco County Transportation Authority, is being closely watched because it is the first P3 project under the new Section 143 of the California Streets & Highways Code, which permits Caltrans and regional transportation agencies to work with the private sector in developing transportation facilities in the state (for more about Section 143, see 'California Passes First Significant Transportation PPP Law in 20 Years').

The CTC vote was a topic of discussion at the California Public Infrastructure Advisory Committee meeting this week, which preceded the Public Infrastructure Financing Forum held at the California Science Center in Los Angeles.

Caltrans plans to issue the final RFP on June 29, 2010.