The Maryland "Purple Line" Transit Project Releases its Final Request for Proposals

On July 28, 2014, the Maryland Transit Administration (MTA) and Maryland Department of Transportation (MDOT) issued the final request for proposals for a public-private partnership to design, build, finance, operate and maintain the Purple Line light rail transit project using an availability payment approach.  The Purple Line is a 16-mile route extending from New Carrollton in Prince George’s County to Bethesda in Montgomery County, with 21 stations and three links to the Washington DC, Metro and MARC commuter train systems.  The Purple Line has estimated project value of $2.37 billion, with the private sector expected to invest between $500 million and $900 million.  The winning concessionaire will be expected to operate and maintain the project for 30 years after construction (roughly 35 years overall).

Legislative and regulatory efforts to kick off the procurement began in earnest in mid 2013, with release of a request for qualifications issued in November 2013.  Four consortia were shortlisted and initial industry review of the proposal documents and draft contract began in February 2014.

The Purple Line has, as among its champions, Lt. Governor Anthony Brown.  MTA/MDOT also enjoys considerable federal support for the Purple Line, with the Obama Administration allocating $100 million toward construction costs in its March 2014 budget submission to Congress.  A full funding grant agreement is expected from the Federal Transit Administration and the Purple Line is seeking further federal funding support through FTA’s New Starts Program.

Proposals are due in January 2015, with the preferred proposer selected as the concessionaire in spring 2015.  Subject to approval by the Maryland Board of Public Works, the concessionaire would likely begin construction by the end of 2015.

More information can be found on MDOT’s website including the primary RFP documents located under Public-Private Partnerships.

Simon Santiago and Katherine Bourdon contributed to this post.

Nossaman’s 30-plus infrastructure attorneys offer clients, colleagues, strategic partners and industry media a wealth of practical experience, insider insight and thoughtful analysis here on Infra Insight. We blog about what we know best, from industry-leading procurements to local and national policy developments that affect the market and our clients.

Stay Connected

RSS RSS Feed

Categories

Archives

View All Nossaman Blogs
Jump to Page

Nossaman LLP Cookie Preference Center

Your Privacy

When you visit our website, we use cookies on your browser to collect information. The information collected might relate to you, your preferences, or your device, and is mostly used to make the site work as you expect it to and to provide a more personalized web experience. For more information about how we use Cookies, please see our Privacy Policy.

Strictly Necessary Cookies

Always Active

Necessary cookies enable core functionality such as security, network management, and accessibility. These cookies may only be disabled by changing your browser settings, but this may affect how the website functions.

Functional Cookies

Always Active

Some functions of the site require remembering user choices, for example your cookie preference, or keyword search highlighting. These do not store any personal information.

Form Submissions

Always Active

When submitting your data, for example on a contact form or event registration, a cookie might be used to monitor the state of your submission across pages.

Performance Cookies

Performance cookies help us improve our website by collecting and reporting information on its usage. We access and process information from these cookies at an aggregate level.

Powered by Firmseek